Contractual ADC (Average Daily Cost)

Charlie Troccaz avatar
Written by Charlie Troccaz
Updated over 3 months ago

The Contractual ADC (Average Daily Cost) means the cost of a resource when working on a project/delivery (or positioned on an opportunity).

Here is the detail of the formula in order to calculate it:


For an internal resource

Contrat ADC = Salary ADC + Contractual advantages ADC + Contractual expenses ADC

Salary ADC =[(monthly gross salary x charges) x 12] / number of annual working days

Contractual advantages ADC = Contractual advantages cost per day

Contractual expenses ADC = Contractual expenses cost per day


For an external resource

Contrat ADC = excluding tax daily rate + (possible contractual advantages and contractual expenses ADC)